Ardsley Chase 6/3/13 Construct Update
Release Date: June 03, 2013
6/3/13 Toll Ardsley Chase - Construction Schedule for next 2 weeks (subject to change & weather):
-
Road A (Lot# 15) Storm Sewer
-
Ardsley Road – Water service terminations at Monaco & Nunez (Road work scheduled for Tuesday and Wednesday 6/4 and 6/5 with police)
-
Ardlsey Road – Milling and Top-Course Paving (Tentatively scheduled for 6/6 and 6/7)
-
Erosion control maintenance
The next schedule update will be submitted on 6/14/13. Thank you,
|